Proposed Commercial Development Process
All proposed commercial development must have the Development Permit Application approved PRIOR to the Building Application being reviewed. Construction CANNOT begin until the Building Application has been approved and a Building Permit has been issued.
All proposed commercial developments submitted must include the following:
- Development Permit Application
- Geotechnical report (if required)
- Real Property Report (Surveyor’s Certificate) showing the site plan for proposed development
- Required forms for Building Official (checklist, analysis form, email consent form, spec sheet (if applicable)
- Energy Code compliance form
- All construction and use information
If the Development Permit is approved then you will be required to submit:
- Commercial Building Permit Application
- Any updated report or construction details